Phase 0 Networking

From Interlock Rochester Wiki

Jump to: navigation, search

Contents

Phase 0 Networking

Overview

This project is to setup initial networking at Interlock

Goals

  1. Make Long Term Decisions
  2. Keep costs to a minimum
  3. Keep the network simple and manageable

Needs

  • 24 port switch that supports vlans
  • DMARC board - Complete --MadScientist 14:03, 26 January 2010 (UTC)
  • 12 x 6-port white wall plates
    • Bought? ETA? --Joshshua 15:12, 24 February 2010 (UTC)
    • Being bought - Out of stock for for a week or so. --MadScientist 03:02, 25 February 2010 (UTC)
  • 75 x black keystone jacks
    • Bought? ETA? What happened to multiple colors? --Joshshua 15:12, 24 February 2010 (UTC)
    • Being bought. Should arrive next week. See below comment about colors --MadScientist 03:02, 25 February 2010 (UTC)
  • 10 x wall boxes - To be donated by neighbor Tim? --Joshshua 15:12, 24 February 2010 (UTC)
  • 60 x cat5(e) - Obtained

Wants

not covered in this project

  • wall conduit
    • If this is not done before pulling wire, it won't be so easy to do. --Joshshua 15:12, 24 February 2010 (UTC)
    • If we ever do add conduit, we will use two piece so that it can be added easily. --MadScientist 03:02, 25 February 2010 (UTC)
    • Decided to plan on raceway after the fact and reach out to members --Antitree 16:15, 26 February 2010 (UTC)
  • gigabit network capabilities
  • cisco catalyst 5505 Route & Switch Module
  • LDAP server
  • second VPN server
  • 2600 Router

Tasks

Subtasks to complete the project. Users are points of contacts on their subjects.

  • Purchase Supplies: (See above)2/26 AntiTree
  • DMARC:
  • LAN/Firewall Services:
    • PfSense: Ben 3/9
    • Switch Configuration: 3/9
  • Wiring:
    • Run network dropsTim

Costs

  • Wall Plates
  • Keystone jacks
  • Wall boxes
    • Confirmed Tim will hook us up. --Antitree 16:21, 26 February 2010 (UTC)
    • FREE!
  • J Hooks
    • Purchased 2/25 should arrive --Antitree 14:58, 26 February 2010 (UTC)
    • $31.21
    • Received 3/1
  • Wire Wraps
    • purchased 2/26
    • $26.13 (2 x 5 yard rolls)

Used Resources

  • PFsense Firewall
  • Cisco 2950 24 port Switch

Physical Layout

Physical Layout Diagram
  • Drops will have a service loop of at least 5' (Approx 2 loops)
  • Bundles will be secured with velcro so that they can be modified
  • The server cabinet will have its own switch to minimize cable mess between the racks
  • The relay rack will need to be bolted to the floor
  • Cables will be run through hooks on the ceiling or along conduit on the walls
  • Since the cable supply is a mix of Cat5 and Cat5e, it will be ensured that each box has at least two runs of Cat5e